Page 201 - PT Kilang Pertamina Balikpapan
P. 201

196





          potensi Koreksi  penambahan  pajak  atas             potential  Correction  of  additional  tax  on
          transfer pricing transaksi tolling antara            transfer  pricing of Intermediate  tolling
          pt KpI dan pt KpB                                    transactions between pt KpI dan pt KpB

          Penyebab risiko ini adalah Direktorat Jenderal Pajak berpendapat   The  cause  of  this  risk  is  that  the  Directorate  General  of  Taxes
          transaksi  tolling  antara  Pt  kPi  dan Pt  kPB  tidak  berdasarkan   believes that the tolling transactions between Pt kPi and Pt kPB
          prinsip  arm’s  length  transaction.  Dampak  dari risiko  ini adalah   are not based on the arm’s length transaction principle. the impact
          adanya koreksi dan denda/sanksi perpajakan.          of this risk is correction and tax fines/sanctions.
          rencana mitigasi yang disiapkan adalah:              the mitigation plans prepared are:
            a.  Dokumentasi  transaksi  afiliasi  di  dalam  Transfer Pricing   a)  Affiliate transaction documentation in the Transfer Pricing
               Documentation.                                        Documentation.
            b.  menyiapkan studi komprehensif sebagai dasar penentuan   b)  Prepare a comprehensive study as the basis for determining
               tolling fee secara arm’s length.                      the tolling fee on an arm’s length basis.


          Keterlambatan penyelesaian unit rfCC                 rfCC unit Completion delays
          Penyebab  munculnya risiko akibat keterlambatan  Engineering   Causes of risks arising from delays in Engineering unit rFCC, delays
          unit  rFCC, keterlambatan  delivery  material/equipment-descoping   in delivery of materials/equipment-descoping within the scope of
          lingkup  Vendor  kNm, isu subkontraktor  yang tidak  perform, dan   kNm Vendors, issues of non-performing subcontractors, and low
          produktivitas produktivitas konstruksi rendah, lack of supervision   productivity. the impact of this risk is the delay in the completion of
          transportasi  material  dari  kariangau, belum adanya  kesepakatan   the project as a whole.
          final mengenai additional cost (cost impact) yang diajukan Jo yang
          menjadi conditional atas komitmen kontraktor terhadap schedule
          rFs 002. Dampak dari risiko ini adalah keterlambatan penyelesaian
          proyek secara keseluruhan.
          rencana mitigasi yang telah disiapkan adalah:        the mitigation plans that have been prepared are:
            a.  melakukan prioritisasi penyelesaian dokumen Engieeering.  a)  Prioritize completion of Engineering documents.
            b.  monitoring dan expiditing progres manufacturing masing-  b)  monitoring  and expediting  the manufacturing  progress of
               masing vendor (assign resident expediter).            each vendor (assignment resident expediter).
            c.  menerapkan metode konstruksi  modular structure  untuk   c)  applying  the modular structure  construction  method  for
               steel structure di Area Equipment Vessel Unscoping KNM.  steel  structures in the  KNM Unscoping  Vessel  Equipment
            d.  monitoring dan follow-up penggantian subkontraktor oleh   area.
               Jo dengan melakukan direct hired pekerja.          d)  monitoring and follow-up of replacement of subcontractors
            e.  Penyediaan fasilitas pekerja (smoking shelter, dining room/  by Jo by direct hiring of workers.
               refreshment  shelter dan  worker welfare facility) untuk   e)  Provision of worker facilities (smoking shelter, dining room/
               meningkatkan efective working hour.                   refreshment shelter, and worker welfare facility) to increase
            f.  Pemenuhan  manpower di sisi  owner untuk  pengawasan   effective working hours.
               proyek yang lebih menyeluruh.                      f)  Fulfillment  of  manpower  on  the  owner’s  side  for  more
            g.  Penyediaan dedicated material controller untuk pengiriman   thorough project supervision.
               material dari kariangau ke site.                   g)  Provision of a dedicated  material controller for material
            h.   Percepatan pembahasan dan finalisasi additional cost/cost   delivery from kariangau to the site.
               impact di internal Pt kPi dan Pt kPB.


          Keterlambatan penyelesaian unit oSBL                 oSBL unit Completion delays
          Penyebab risiko  ini yakni  keterlambatan pengiriman  material/  There are 5 (five) causes of this risk, namely delays in Black Start-
          equipment  OSBL,  subkontraktor  tidak  perform  dan kurangnya   up  unit  construction  work,  delays  in  delivery  of  osBL  materials/
          manpower,  produkivitas  pekerja  konstruksi yang rendah,  dan   equipment, non-performing subcontractors, and lack of manpower,
          kurangnya  supervisi  oleh  kontraktor di setiap area.  Dampak dari   low productivity of construction workers, and lack of supervision.
          risiko ini adalah keterlambatan proyek secara keseluruhan.  the impact of this risk is the overall project delay.

          rencana mitigasi yang disiapkan manajemen Pt kPB adalah:  the mitigation plan prepared by Pt kPB’s management is:
            a.  Expiditing progres manufacturing  vendor  peralatan  osBL   a.  setting up a  tie-in facility  for the  needs  of the existing
               dan material (assign dedicated expediter).            Utilities Black Start-Up from the existing RU V Refinery.
            b.  monitoring dan follow-up penggantian subkontraktor oleh   b.  Expediting  progress of manufacturing  vendors  of  osBL
               Jo dengan melakukan direct hired pekerja.             equipment and materials (assign dedicated expediter).
            c.  Peyediaan  fasilitas  Pekerja (smoking shelter, dining   c.  monitoring and follow-up of replacement of subcontractors
               room/refreshment  shelter, worker welfare facility)  untuk   by Jo by direct hiring of workers.
               meningkatkan efektivitas jam kerja.                d.  Provision  of  employee facilities  (smoking shelter,  dining
            e.  Pemenuhan  manpower di sisi  owner untuk  pengawasan   room/refreshment  shelter, worker  welfare facility) to
               proyek yang lebih menyeluruh.                         increase the effectiveness of working hours.
            e.  Penyediaan  dedicated  pengawas untuk masing-masing   e.  Fulfillment  of  manpower  on  the  owner’s  side  for  more
               area osBL.                                            thorough project supervision.
                                                                  f.  Provision of dedicated supervisors for each osBL area.





         PT Kilang Pertamina Balikpapan                                    Laporan Tahunan Tahun Buku 2022 Annual Report