Creating an Environmentally Friendly Refinery, the Lifting Spray Tower was Successfully Carried Out at the Balikpapan RDMP Project

#SobatKilang, one of the important equipment in the Balikpapan RDMP project called Spray Tower with tag number A-052-10-C1 was officially installed on Friday (31/3) morning. Even though it was hot in the holy month of Ramadhan, this did not dampen the enthusiasm of the Officers and all Balikpapan RDMP Project...

Read More
2
2023 February

Progress of the Balikpapan RDMP Managed by PT Kilang Pertamina Balikpapan (KPB), Modification of the P-7 Tank Has Been Completed

The P-7 tank is a tank with an Internal Floating Roof (IFR) with a capacity of 35 thousand barrels. During the course of the RDMP project, the P-7 tank will be utilized to increase the allocation of storage tanks for light naphtha products. Well, Light Naphtha is an important component...

Read More
7
2023 January

Enthusiastic About the Progress of Balikpapan RDMP, RFCC Stripper Column Successfully Installed

One of the important milestones in the Balikpapan RDMP Project is that the Stripper Column & Primary Absorber with code C-052-25/C-052-26 has been successfully installed. This 617 ton device functions to maintain the quality and quantity of LPG and Gasoline from the RFCC unit. The method of installing this column...

Read More
26
2022 November

It's Official, Emergency Diesel Generator (EDG) Generation Successfully Carried Out: One Definite Step Toward Operation of the Balikpapan RDMP Refinery

Pertamina's dedication in supporting the National Strategic Project (PSN) Refinery Development Master Plan (RDMP) in Balikpapan is proven by its success in achieving vital milestones. After successfully installing the Gas Turbine Generator (GTG) and Steam Turbine Generator (STG) as the main generator series to support the electrical utilities of the...

Read More
16
2022 June

Deisohexanizer, Important Equipment to Produce Gasoline Products Successfully Installed

PT Kilang Pertamina Balikpapan (KPB)'s commitment to optimizing the performance of the Refinery Development Master Plan (RDMP) Project was carried out through achieving an important milestone, namely by starting to install Deisohexanizer Equipment with the C-082-17 series. This tool is an important part of the somerization unit which functions to...

Read More
8
2022 June

SAFETY FIRST!!! PT Refinery Pertamina Balikpapan (KPB) Successfully Holds Grand Safety Talk

Balikpapan, June 2022 - In order to create safe working conditions and behavior in the field, the Grand Safety Talk and Reward are considered effective in conveying work safety aspects to increase the active role and potential of workers in realizing K3 culture in the work area and implementing Values...

Read More