Page 13 - 2020 Annual Report
P. 13
Tata Kelola Tanggung Jawab Sosial
Perusahaan Corporate Social
Good Corporate Responsibility
Governance
PeriSTiwa PenTing 2020
IMpORTANT EvENTs 2020
Triwulan Pertama
first Quarter
• Penyelesaian novasi Kontrak ePc iSBL-oSBL
• memulai pekerjaan piling dan stone column di area residual fluid catalytic cracking (rfcc)
• memulai instalasi residual fluid catalytic cracking (rfcc) feed Tank d-320-12, 02a/B
• memulai Principal agreement dengan salah satu calon equity partner
• completed the novation of ePc iSBL-oSBL contract
• Started the Piling & Stone column work at residual fluid catalytic cracking (rfcc) area
• Started the installation of Storage Tank d-320-12, 02a/B
• Started the Principal agreement with the candidate of equity partner
Triwulan Kedua
Second Quarter
• Penyelesaian novasi Kontrak Project management consultant (Pmc)
• Pencapaian operational acceptance Proyek relokasi acid flare
• Persetujuan L3 Schedule Proyek ePc Lawe-Lawe
• completed the novation of Project management consultant (Pmc) contract
• operational acceptance of relocation acid flare Project
• approved the L3 Schedule ePc Lawe-Lawe
Triwulan Ketiga
Third Quarter
• memulai aktivitas P&id review meeting unit Sulfur recovery unit (Sru) dan hydrogen
manufacturing unit (hmu)
• memulai pekerjaan pondasi gas Turbine generator Train 1
• Pencapaian operational acceptance Proyek Jetty Sulfur Baru & dredging
• Started the P&id review meeting of Sulfur recovery unit (Sru) and hydrogen manufacturing
unit (hmu)
• Started the foundation work of gas Turbine generator Train 1
• operational acceptance of new Sulphur Jetty & dredging Project
Triwulan Keempat
fourth Quarter
• Penerbitan Purchase order (Po) Single Point mooring (SPm) ePc Lawe-Lawe
• Penerbitan Purchase order (Po) onshore & offshore Pipeline (20” & 52”) ePc Lawe-Lawe
• Pelaksanaan erection 2 unit gas Turbine generator (gTg), 2 unit heat recovery (hrSg), dan 2
unit Boiler
• Penyelesaian mechanical installation Tangki d-320-12
• issued Po SPm ePc Lawe-Lawe
• issued Po onshore & offshore Pipeline (20” & 52”) ePc Lawe-Lawe
• erection 2 unit of gTg, 2 unit of hrSg, and 2 unit of Boiler
• completed the mechanical installation Tank d-320-12
PT Kilang Pertamina Balikpapan 13 Laporan Tahunan 2020 | Annual Report 2020